This is where we will inform the community with updates on the current Levee project
Pat Braziel, Chair
Eileen Ricker, Secretary
Marc Madrigal, ROCA Liaison
Steven Macilraith, Golf Liaison
Mark Wellendorf, Website/IT Board Liaison
Johanna Williams, Board Liaison
A link to frequently asked questions
https://www.spk.usace.army.mil/Missions/Civil-Works/Natomas-Basin/Reach-A/
PROJECT UPDATES
October 20, 2020, 3:42PM, SAFCA Update
The 3473 Swallow’s Nest Lane Demolition Project has been delayed due to the additional time required by PG&E to disconnect the gas service to the house. It is likely the demolition will occur in mid-November to early December timeframe. The demolition contractor will provide an updated schedule when he has more certainty from PG&E as to when they will be performing the gas line disconnection.
Levee Project Update…September 09, 2020
3473 Swallows Nest Ln, in advance of any work taking place on or near the site.
GEI Consultants will be performing the noise evaluation for SAFCA.
GEI personnel will be coming to the site beginning on Thursday, 09/10 through Monday 09/14
and will limit their access to SAFCA-owned property where they will temporarily stage their
noise monitoring equipment.
The surveying at Swallows Nest was for the relocation of the utilities. The surveying for the property acquisition will be done later. The "Right Of Entry" is good for 6months and stated they would need 2 days for that work. We will be advised when they will be here so we can notify the community.
The paint markings and stakes were used to assist the survey crew in tracking topography limits and the locations of temporary control points. The stakes can be removed and do not denote any utility locations or boundary lines of any kind.
Levee Project Update…August 27, 2020
Levee Project Update…August 16, 2020
SAFCA’s acquisition of the house at 3473 Swallow’s Nest Lane has been completed and will be removed within 90-120 days. The contractor is developing a schedule of activities related to the removal and a detailed timeline will be provided on our website.
The Army Corps has indicated the levee construction adjacent to Swallow’s Nest will occur in 2022-2023. Utility relocations, including water and electrical lines, will be completed prior to levee construction and are anticipated to occur in 2021.
Levee Project Update…August 14, 2020
Surveyors and SAFCA will be on site at Swallows Nest Friday August 14th.
Subject: SAFCA Acquisition and Demolition Status of
3473 Swallows Nest Lane, Sacramento CA
APN 274-0560-044
1.As outlined in the June 10, 2020 Memo from John Bassett, SAFCA anticipates that the demolition process for the residential structure located at 3473 Swallows Nest Lane can likely be completed within the next 90-120 days. There is always uncertainty associated with any type of construction, particularly with utility coordination, and therefore any dates and timelines are of a fluid nature.
Steps for Residential Structure Demolition
Previous owner officially abandons property – anticipated to occur by June 17
Hazardous materials testing and evaluation – can take 2-3 weeks. Sampling was conducted on June 12. SAFCA is awaiting analysis results.
Contractor to obtain City permit to demolish structure
Utility disconnections- coordination with utility providers:
In addition, per our recent discussions, SAFCA is evaluating use of the City ramp adjacent to 3473 Swallows Nest Lane as the ingress/egress point for the contractor in order to minimize travel through interior streets.
Beyond site restoration, SAFCA will be requesting input from Swallow’s Nest on:
Office 916-874-7606
Fax 916-874-8289
1007 7th Street, 7th Floor
Sacramento, CA 95814-3407